Building Contract Claims, 4th Edition

by ; ;
Edition: 4th
Format: Hardcover
Pub. Date: 2008-10-01
Publisher(s): Wiley-Blackwell
Availability: This title is currently not available.
  • Free Shipping Icon

    Receive Free Shipping To The More Store!*

    *Marketplace items do not qualify for the free shipping promotion.

List Price: $164.99

Rent Textbook

Select for Price
There was a problem. Please try again later.

New Textbook

We're Sorry
Sold Out

Used Textbook

We're Sorry
Sold Out

eTextbook

We're Sorry
Not Available

Summary

This book established itself as the leading work on the subject of claims under building contracts when it was first published in 1983. It explains the legal basis of contractor's claims under all the main building contracts and considers the practical implications. The new edition is a substantial revision and considers the latest editions of the JCT forms, two new JCT contracts, the New Engineering Contract, and new case law since the last edition.

Author Biography

BA, MA, PhD, RIBA, David Chappell Consultancy Ltd, Wakefield

Table of Contents

Preface ix
Acknowledgements xii
Contract abbreviations xiii
Part I 1(156)
1 Introduction
3(15)
1.1 Structure of the book
3(1)
1.2 Definitions
3(5)
1.3 The basis of claims
8(2)
1.4 Architect's and contract administrator's powers and liability to the contractor
10(4)
1.5 Quantity surveyor's powers
14(4)
2 Time
18(24)
2.1 Time of the essence
18(1)
2.2 Time at large
19(2)
2.3 Extension of time clauses in contracts
21(3)
2.4 Concurrency
24(5)
2.5 Acceleration
29(5)
2.6 Sectional completion
34(2)
2.7 The SCL extension of time protocol
36(6)
3 Liquidated damages
42(25)
3.1 The meaning and purpose of liquidated damages
42(1)
3.2 Liquidated damages or penalty
43(5)
3.3 Liquidated damages as limitation of liability
48(1)
3.4 Sums greater than a genuine pre-estimate
49(1)
3.5 Liquidated damages as an exhaustive remedy
50(4)
3.6 Injunction
54(2)
3.7 Liquidated damages in relation to loss
56(1)
3.8 Where there is no breach of contract
57(2)
3.9 Calculation of liquidated damages
59(2)
3.10 Maximum recovery if sum is a penalty
61(2)
3.11 Maximum recovery if liquidated damages do not apply
63(2)
3.12 Bonus clauses
65(2)
4 Basis for common law claims
67(19)
4.1 General
67(2)
4.2 Implied terms in building contracts
69(5)
4.3 Variation of contract
74(1)
4.4 Omission of work to give it to others
75(1)
4.5 Extra work
76(2)
4.6 Possession of site
78(4)
4.7 Site conditions
82(4)
5 Direct loss and/or expense
86(5)
5.1 Introduction
86(1)
5.2 Direct versus indirect
87(4)
6 Potential heads of claim
91(41)
6.1 Basic principles
91(2)
6.2 Two basic claims situations
93(3)
6.3 Foreshortened programme
96(2)
6.4 The 'knock-on' effect
98(3)
6.5 The more common heads of loss
101(30)
6.6 Cost of a claim
131(1)
7 Causation
132(8)
7.1 Theory
132(2)
7.2 Use of networks
134(2)
7.3 Float
136(4)
8 The global approach
140(8)
9 Substantiation of claims
148(9)
9.1 Principles
148(3)
9.2 Nature of supporting evidence
151(4)
9.3 'Scott Schedule'
155(2)
PART II 157(206)
10 Extension of time under JCT standard form contracts
159(62)
10.1 Extension of time position under JCT 98
159(31)
10.2 Extension of time position under IFC 98
190(5)
10.3 Extension of time position under MW 98
195(2)
10.4 Extension of time position under WCD 98
197(6)
10.5 Extension of time position under PCC 98
203(5)
10.6 Extension of time position under MC 98
208(4)
10.7 Extension of time position under TC/C 02
212(5)
10.8 Extension of time position under MPF 03
217(4)
11 Liquidated damages under JCT standard form contracts
221(12)
11.1 Liquidated damages position under JCT 98
223(2)
11.2 Liquidated damages position under IFC 98
225(1)
11.3 Liquidated damages position under MW 98
226(1)
11.4 Liquidated damages position under WCD 98
227(1)
11.5 Liquidated damages position under PCC 98
228(1)
11.6 Liquidated damages position under MC 98
229(2)
11.7 Liquidated damages position under TC/C 02
231(1)
11.8 Liquidated damages position under MPF 03
232(1)
12 Loss and/or expense under JCT standard form contracts
233(54)
12.1 Introduction
233(1)
12.2 Under JCT 98
234(28)
12.3 Under IFC 98
262(6)
12.4 Under MW 98
268(2)
12.5 Under WCD 98
270(7)
12.6 Under PCC 98
277(3)
12.7 Under MC 98
280(1)
12.8 Under TC/C 02
281(3)
12.9 Under MPF 03
284(3)
13 Variations
287(76)
13.1 Introduction
287(1)
13.2 The baseline
288(1)
13.3 Bills of quantities
289(3)
13.4 Functions of the architect and the quantity surveyor
292(1)
13.5 Variations position under JCT 98
293(29)
13.6 Variations position under IFC 98
322(8)
13.7 Variations position under MW 98
330(2)
13.8 Variations position under WCD 98
332(13)
13.9 Variations position under PCC 98
345(2)
13.10 Variations position under MC 98
347(1)
13.11 Variations position under TC/C 02
348(10)
13.12 Variations position under MPF 03
358(5)
PART III 363(126)
14 Claims under GC/Works/1 (1998)
365(17)
14.1 Introduction
365(1)
14.2 Valuation of instructions
365(4)
14.3 Prolongation and disruption
369(4)
14.4 Extension of time and liquidated damages
373(9)
15 Claims under ACA 3
382(26)
15.1 Introduction
382(1)
15.2 Monetary claims under ACA 3
383(7)
15.3 Architect's instructions
390(5)
15.4 Extension of time and liquidated damages
395(12)
15.5 Claims on the final certificate
407(1)
16 Claims under NEC
408(29)
16.1 Introduction
408(1)
16.2 Compensation events
409(26)
16.3 Delay damages
435(2)
17 Sub-contract claims
437(52)
17.1 Introduction
437(1)
17.2 Sub-contract form NSC/C
437(17)
17.3 Domestic sub-contract form DSC
454(13)
17.4 Sub-contract conditions for sub-contractors named under IFC 98 (NAM/SC)
467(5)
17.5 The IN/SC form of domestic sub-contract for use with IFC 98
472(1)
17.6 The Works Contract/2 for use with MC 98
473(10)
17.7 The ACA form of sub-contract
483(6)
APPENDICES 489(35)
Appendix A: Example of build up of contractor's entitlement to reimbursement of direct loss and/or expense under JCT 98, clause 26
491(23)
Appendix B: Extension of time and money claims under DOM/1
514(10)
Table of cases 524(12)
Table of standard form contract clauses 536(8)
Index 544

An electronic version of this book is available through VitalSource.

This book is viewable on PC, Mac, iPhone, iPad, iPod Touch, and most smartphones.

By purchasing, you will be able to view this book online, as well as download it, for the chosen number of days.

Digital License

You are licensing a digital product for a set duration. Durations are set forth in the product description, with "Lifetime" typically meaning five (5) years of online access and permanent download to a supported device. All licenses are non-transferable.

More details can be found here.

A downloadable version of this book is available through the eCampus Reader or compatible Adobe readers.

Applications are available on iOS, Android, PC, Mac, and Windows Mobile platforms.

Please view the compatibility matrix prior to purchase.